Details of interior, exterior work explained to board

Coinciding with the winter season, construction at Glenwood Elementary has moved from the exterior to the interior as progress continues.

Chad Stevers of Gilbane Building Co. provided an update on work at the Rossford Board of Education’s December meeting.

At the Glenwood elementary complex, he said, “all brick is on and windows are in. We’re starting to put ceiling grid in and stairs are being poured. Restrooms are ready for tile and paint.”

Drywall also has been installed in many areas, he added.

Mr. Stevers noted that the cafeteria and gym ceiling and duct work have been painted.

In addition, the academic and administrative area is nearing completion of all interior framing.

The Glenwood site is scheduled to open in August.

 

To read more please log in or subscribe to the digital edition https://www.etypeservices.com/Welch%20PublishingID444/

Welch Publishing

Perrysburg Messenger Journal
130 Louisiana Ave.
Perrysburg, OH 43551

419-874-4491

Rossford Record Journal
130 Louisiana Ave.
Perrysburg, Ohio 43551

419-874-4491

Holland-Springfield Journal
130 Louisiana Ave.
Perrysburg, OH 43551

419-874-4491

Point and Shoreland Journal
130 Louisiana Ave.
Perrysburg, OH 43551

419-874-4491